Advertisement

Headquarters still in a fix

First phase of repairs at police and fire building is about done, and the next phase will cost about $11 million.

June 10, 2009|By Christopher Cadelago

CITY CENTER — Even as the city prepares to close the first chapter of repairs to botched work on the $30-million police and fire headquarters, the second act is expected to bring the total project cost to nearly half the price of the original building 11 years ago.

Following the City Council’s approval of an additional $236,185, the total price for the first phase of repairs now stands at $1.34 million, but the second phase, scheduled to begin in 2010, is expected to carry a price tag of roughly $11 million.

The first phase of work, expected to be finished July 24, included repairs to address immediate public safety risks posed by water intrusion that damaged portions of the building.

Advertisement

While in the process of removing the limestone flooring, crews discovered that the structural concrete slab had been ground down by 1.5 inches, leaving the lobby in an unsafe condition, officials said.

“Once they took the stone off, that’s when we found out that somehow, somewhere, somebody had ground the concrete too thin,” said Ari Omessi, assistant public works director.

Omessi said crews completed repairs to the floor and laid limestone in the main lobby, throughout the Fire Department and on about half of the Police Department’s portion of the building, a process that will bring the load-bearing capacity from roughly 80 pounds per square foot to 110 pounds per square foot at a cost of $167,569.

The complete change order also includes traffic coating on the ramp to the parking garage, roof fall protection, planter waterproofing, basement floor painting, repairs to the main doors and lobby and museum windows.

All of the issues stem from the original construction of the building, Omessi said.

The council in September 1995 awarded a contract on the building at 200 N. Third St. to Kajima Construction Services. The $30-million building, completed in 1998, began to show water damage after the first rains, Omessi said, and in 2000, firefighters discovered water damage in and around the shower area, according to a city report.

The Public Works Department spent $140,000 to remove mold and rebuild the showers.

Burbank officials later discovered water leaks from the parking structure, front stairs and street-facing windows, some of which were installed backward.

Burbank Leader Articles
|
|
|