Verdugo pool opening pushed back

Design changes, slow plan approval have been problems, officials say.

April 21, 2012|By Maria Hsin, maria.hsin@latimes.com
  • The empty swimming pool at Verdugo Park. The pool has been closed since 2009, and was a former training site for the 1984 Olympics.
The empty swimming pool at Verdugo Park. The pool has been… (Tim Berger / Staff…)

The edges of the signs posted on the doors and windows have started to curl, but the message is just as clear as it was nearly four years ago: The Verdugo Park pool is closed.

Since 2008, the swimming pool has sat empty. Once a 1984 Olympics training site, dirty water and leaves now accumulate in the pool's deep end.

City officials in 2010 said the pool could be operational by fall 2011. Then in July of that year, Councilman Dave Golonski indicated the pool could be open by summer 2012.

But now even that goal has been pushed back, meaning residents expecting a poolside reprieve from the summer heat will have to look elsewhere.

“I've been waffling back and forth about whether to write another letter to the editor, but wanted to wait until the bids were in and we're actually moving forward before I made another projection,” Golonski said. “I'm hoping that we will have a solid time frame when we award the bid. All the bids are in, they were evaluated and we are ready to award the bid. Once we get to that point, we can say with some degree of certainty [what the timeline will be.]”

Advertisement

Golonski said he also wanted to better understand why the project was delayed.

“My biggest disappointment is we have a pool, a big asset, and the community hasn't been able to use it for four years,” Golonski said. “It's hot in the summer and having a closed pool is not a good thing.”

“The pool was closed for a number of structural and mechanical issues in 2008, after 60 years,” said Sean Corrigan, assistant director of city engineering. “My job is to finish the design with the architect and go to bid.”

Once construction begins, it could be nine months to a year before the pool is open, said Pat Thomas, recreational services manager for the city.

Design changes were made in early 2011 to the project — budgeted at $7.3 million — and a construction contract could be awarded next month, Corrigan said.

Design changes were made for better safety and security, including moving walls and shade structures so lifeguards have a better view of the pool from different angles and within the locker room building, Corrigan said.

“It's more cost effective to do the changes before we go to bid, rather than during construction,” he said.

Another reason for the delay had to do with the Los Angeles County Health Department's inspection, Corrigan said, which he said “took longer than anticipated.”