THE818NOW
May 3, 2013
The California bullet train agency on Thursday defended its bidding criteria for selecting the winner for its first construction contract, saying that the process held down prices and was handled properly. The California High-Speed Rail Authority has come under fire from critics who assert changes to the bidding criteria could jeopardize the quality of the project. The authority tentatively chose a team led by Sylmar-based Tutor Perini to build a 29-mile segment of track through Fresno even though it had the lowest technical score.
THE818NOW
April 30, 2013
California's bullet train agency is facing a series of new regulatory and political problems that could jeopardize its July construction kickoff, which already has been delayed more than six months. The new challenges are coming from a private railroad that controls a key right of way, a legislative committee delving into contracting issues and a powerful federal agency asserting authority over the project. The rail agency is beginning to make purchase offers for land around Fresno and says it still plans to start building this summer.
THE818NOW
April 19, 2013
A lawsuit alleging that approval of the high-speed rail system's first sections in the Central Valley violated state environmental laws was settled Thursday, eliminating a legal obstacle that could have delayed construction. A Sacramento County Superior Court judge approved an agreement that calls for the California High-Speed Rail Authority to further reduce the project's effects on farming operations, preserve agricultural land and provide additional compensation for landowners.
THE818NOW
April 19, 2013
State high-speed rail officials acknowledged Thursday that they changed their rules for selecting a builder for the bullet train's first phase in the Central Valley, a shift that subsequently made it possible for a consortium led by Sylmar-based Tutor Perini to be ranked as the top candidate despite receiving the lowest technical rating. The California High-Speed Rail Authority announced last week that the Tutor Perini-Zachry-Parsons joint venture was the top-rated contender among five bidders seeking to build the initial 29 miles of track between Madera and Fresno.
THE818NOW
March 27, 2013
The California bullet-train project has collided with farmers, political conservatives and wealthy suburbanites who would like to see the $68-billion system killed. Now it is facing tough criticism from an unlikely quarter: within the ranks of high-speed rail's true believers. Some longtime backers of the project are objecting to political compromises that they say undermine legal safeguards for the massive investment, notably a design that would move passengers between urban destinations faster than air travel, as well as requirements intended to prevent a half-built system.
THE818NOW
January 28, 2013
Construction of California's high-speed rail network is supposed to start in just six months, but the state hasn't acquired a single acre along the route and faces what officials are calling a challenging schedule to assemble hundreds of parcels needed in the Central Valley. The complexity of getting federal, state and local regulatory approvals for the massive $68-billion project has already pushed back the start of construction to July from late last year. Even with that additional time, however, the state is facing a risk of not having the property to start major construction work near Fresno as now planned.
THE818NOW
November 27, 2012
A few hundred faithful pass through the doors of Pastor Bob Childress' sanctuary every Sunday, but he worries that sometime in the next decade a 220-mph bullet train may take their place. The future route of the train, as currently drawn, takes dead aim for the Church of the Canyons, an evangelical refuge on Sand Canyon Road in Santa Clarita with a congregation of 450. "This will be an excellent test of our faith," Childress said. California's bullet train has generated plenty of opposition in the areas around the San Gabriel Mountains.
THE818NOW
November 16, 2012
The California High-Speed Rail Authority said Thursday that it was adding 12 months to the construction schedule for 130 miles of track in the Central Valley, easing what some outside experts have contended was an overly aggressive and risky timeline. Jeff Morales, chief executive of the authority, said the revised schedule would have the track completed by December 2017 rather than a year earlier as set under the agency's contracting documents. The new timetable will allow contractors to use less overtime and other practices that were expected under the accelerated plan in place earlier, Morales said.
THE818NOW
November 13, 2012
Civil War veteran William Hood arrived at the mosquito-infested swamps near Bakersfield in 1874 to build a rail line that would soar through the Tehachapi Mountains, linking the Bay Area and Southern California for the first time. Hood, Southern Pacific Railroad's chief assistant engineer, assembled 3,000 Chinese immigrants with picks, shovels and dynamite. They snaked the track up treacherous mountain ridges, twisted it back and forth around canyons and punched it through sheer rock in a series of 18 tunnels - climbing 4,025 vertical feet along the way. It's a feat no one has attempted to duplicate.
THE818NOW
November 1, 2012
Officials at the California bullet train agency have pushed back by months a key milestone in the upcoming construction, though they say the project is not falling behind and that they will be able to build 130 miles of track in the Central Valley by 2017. Jeff Morales, chief executive officer of the project, acknowledged long-standing rumors in the construction industry that the deadline for submitting bids on the first segment would be pushed back from this week to Jan. 18, coming after an earlier revision that pushed the deadline back from September.